As
the
fresh properties of SCC are fundamental to both its short and long term
performance (i.e. they can not be compensated with further compaction)
tighter
controls on materials and production consistent with the stipulated
requirements are therefore required.
Important
Considerations
¶SCC
Production: Production
of SCC requires more experience and care than the conventional vibrated
concrete. The plant personnel would need training and experience to
successfully produce and handle SCC. In the beginning, it may be
necessary to
carry out more tests than usual to learn how to handle SCC and gain the
experience.
Before
any SCC is produced at the plant and used at the job site, the mix must
be
properly designed and tested to assure compliance with the project
specifications. The ingredients and the equipment used in developing
the mix
and testing should be the same ingredients and equipment to be used in
the
final mix for the project.
Most
common concrete mixers can be used for producing SCC. However, the
mixing time
may be longer than that for the conventional vibrated concrete. SCC is
more
sensitive to the total water content in the mix. It is necessary to
take into
account the moisture/water content in the aggregates and the admixtures
before
adding the remaining water in the mix. The mixer must be clean and
moist, and
contains no free water.
Admixtures
for the SCC may be added at the plant or at the site. There is cost
benefit in
adding the admixtures at the site. Conventional ready-mix concrete can
be
bought at a lower cost than the cost of SCC bought from a ready-mix
supplier.
¶
Transportation:
The
truck drivers should be given oral and written instructions for
handling SCC.
The truck drivers must check the concrete drum before filling with SCC
to make
sure that the drum is clean and moist, but with no free water. Extra
care must
be taken for long deliveries. In addition to the usual information, the
delivery
note should show the following information:
- Slump
flow - target value and acceptable range.
- Production
time - time when it was produced.
- Instruction
for adding admixtures at the site, if allowed.
The
truck
drivers should not be allowed to add water and/or admixtures during
transit.
¶
Form
System: All
commonly used form materials are suitable for SCC. For surface quality
of SCC,
wood is better than plywood, and plywood is better than steel. More
pores seem
to form on the surface when the form skin is colder than the SCC.
During cold
weather placement of SCC, it may be necessary to insulate the formwork
to
maintain temperature and normal setting time. SCC is more sensitive to
temperature during the hardening process than the conventional vibrated
concrete.
Due
to the cohesiveness of SCC, the formwork does not need to be tighter
than that
for conventional vibrated concrete.
Higher
form pressures than normal were not observed even at high rate of
concrete
placement. However, it is recommended that the formwork be designed for
hydrostatic pressure, unless testing has shown otherwise.
¶
Casting
on Site: A
pre-SCC placement meeting with all personnel involved in the SCC
placement
would be beneficial. The SCC placement plan, including QC/QA, and the
roles and
responsibilities of the field personnel should be explained and
understood.
In
addition to the normal testing, the slump flow, T50 and L-box tests are
useful
to check SCC at the job site before placement.
SCC
can flow horizontally a distance of 15 to 20m without segregation. A
well-designed SCC may have a free fall of as much as 8m without
segregation.
However, it is recommended that the distance of horizontal flow be
limited to
10m and the vertical free fall distance be limited to 5m.
For
deck slab of a bridge, it would be difficult for the SCC to flow too
far. This
could be handled by designing an SCC with a lower slump flow. With a
lower
slump flow, a bridge deck with a slope of 2% could also be
accomplished.
If
an SCC placement is interrupted and the concrete has started to harden,
it
would be necessary to "wake up" the placed concrete by striking a
stick or board into the concrete several times before starting the
placement
again.
SCC
takes some time before the hardening starts, especially during cold
weather
conditions. When it starts to harden, the process is very rapid, which
can
cause problems in leveling and treating large surface areas.
¶
Surface
Finishing and Curing: Finishing
and curing of SCC can follow the good practices of superplasticized
high
performance concrete. Surface of SCC should be roughly leveled to the
specified
dimensions, and the final finishing applied as necessary before the
concrete
hardens.
SCC
tends to dry faster than conventional vibrated concrete, because there
is
little or no bleeding water at the surface. SCC should be cured as soon
as
practicable after placement to prevent surface shrinkage cracking.
¶
Cold
Joint: When
placing a new layer of SCC on old SCC, the bond between the old and new
SCC is
equal to or better than in the case of conventional vibrated concrete.
Normal
vibration will not destroy the concrete, such as in the case of placing
conventional vibrated concrete on fresh SCC. This may be necessary when
the
surface slope is greater than practicable for SCC.