| 1 |
10 to 30% passing the 300 μm (No. 50) sieve
and
2 to 10%
to pass the 150 μm (No. 100) sieve
|
Generally allowed by most specifications |
|
2
|
lower limits of above range (given in 1 )
|
adequate for easy placing conditions or for
mechanically finished concrete
|
|
3
|
at least 15% passing the 300 μm (No. 50) sieve
and
3% passing the 150 μm (No. 100) sieve
|
Generally recommended for hand-finished concrete
floors or where a smooth texture is needed
|
|
4
|
15 to 30% passing the 300 μm (No. 50) sieve,
and
5 to 10% passing the 150-μm (No. 100) sieve
|
Recommended when concrete is to be pumped through
lines less than 150 mm (6 in.) in diameter
|