Click to view details.... Click to view details.. Click to view details.... Click to view details.... TERApro- the professional software
 

image
image
Vincent Chu Section
Vincent T. H. Chu renowned internationally as walking encyclopedia of civil engineering answers some of the  most basic yet highly challenging civil engineering questions.........
image
Bridges Concrete
Structures
Roadwork Earthwork
Piles & Foundation


Bridges
1

Under what situation shall engineers use jacking at one end only and from both ends in prestressing work?

2 What is “preset” during installation of bridge bearings?
3 In incremental launching method of bridge construction, what are the measures adopted to  enhance sufficient resistance of the superstructure during the launching process?
4
5

What are the advantages of assigning the central pier and the abutment as fixed piers?

6 Sometimes the side of concrete bridges is observed to turn black in colour. What is the reason for this phenomenon?
7 In prestressing work, if more than one wire or strand is included in the same duct, why should all wires/strands be stressed at the same time?
8 In the design of  elastomeric  bearings, why are steel plates inserted inside the bearings?
9 How to determine the size of elastomeric bearings?
10 In a curved prestressed bridge, how should the guided bearings in piers of the curved region be oriented with respect to the fixed bearing in abutment?
Concrete Structures
1
2 If on-site slump test fails, should engineers allow the contractor to continue the concreting works?
3 What is the function of shear keys in the design of retaining walls?
4
5 What are the major problems in using pumping for concreting works?
6 Article: Control of Maximum Temperature in Concrete
7 Is it desirable to use concrete of very high strength i.e. exceeding 60MPa? What are the potential problems associated with such high strength concrete?
8 What are the disadvantages of curing by ponding and polythene sheets?
9 Comparing the rate of “Formwork exceeding 300mm wide, horizontal or at any inclination up to  and including 5 degree   to the horizontal” with the rate of “Formwork exceeding 300mm wide, at any inclination more than 85 degree  up to and including 90 degree  to the horizontal”, which one is higher?
10
Roadwork
1 How can unreinforced concrete pavement function without mesh reinforcement?
2
3
4 Why is the slump specified in concrete carriageway comparatively low (30mm) when compared with normal concrete (75mm)?
5
6 What is the importance of air void content in bituminous pavements?
7 In concrete pavement, why is the requirement of 95% by mass of quartz grains specified in contract?
8
9 What is the function of a sand layer underlying paving slab /interlocking blocks?
10 What is the function of longitudinal joints in concrete road pavements?
Earthwork
1 In soil compaction test, if a test result exceeds 100%, should engineers accept the result?
2 What are the different applications of draglines, backhoes and shovels?
3
4 Is  it  worthwhile  to  carry  out  tests  on  particle  density  of  soil  particles  for geotechnical design?
5 In  determining  the  effective  stress  parameters  of  a  soil  sample,  which  test  is preferable, consolidated undrained test or consolidated drained test?
6 In conducting triaxial test to determine shear strengths for soil samples, what consolidation pressures should be specified?
7
8
9 What are the main reasons for conducting pull-out tests for soil nails?
10 Are  there  any  differences  in  the  methods  of  compaction  between  clayey  soil material and sandy material?
Piles and Foundation
1
2 How do rock sockets take up loads?
3
4
5
6 In designing the lateral resistance of piles, should engineers only use the earth pressure against pile caps?
7 Some codes limit the ratio of weight of hammer to weight of pile for pile driving. What is the reason behind this?
8
9
10
 
 

ConcreteBasics.org's Newsletter
* indicates required
Question-Answer forum
Submit an article
Photo Gallery