Initial setting time is the time interval for
which the cement products remain in plastic conditions. As such, activities
such as mixing, transporting, placing, compacting & finishing should be
completed within the Initial setting period. The purpose of Initial setting time limit is to ensure that
the user will have sufficient time to place and finish concrete after mixing.
Final setting time can be understood as
the time elapsed between the moment the water is added to the cement, to the
time when the paste has completely lost its plasticity. After placement,
compaction & finishing of concrete, it is desirable that the concrete loses
its plasticity in earliest possible time so that it becomes less vulnerable to
damages from external agencies.
These tests determine compliance to the setting time limits specified by relevant code/ standards.
|